Construction Ended: Winter 2023
Funding Source: Road Maintenance and Rehabilitation Account (RMRA)
Budget: $1,050,000
Background: Asphalt concrete pavement used for roadways and parking lots is one of the City’s largest assets. Regular pavement maintenance is required in order to achieve the full, useful life of the pavement. Slurry sealing the pavement is an effective preventive maintenance strategy. The slurry seal coating provides a protective layer and wearing course for the original pavement structure.
Slurry seal is typically applied every seven years. The City has been divided into seven slurry seal areas. Area 4 was due for this preventative maintenance procedure.
Work
This project included crack seal, application of slurry seal, and replacement of pavement legends and striping.
Project Area
The project area, Area 4, included the neighborhood bounded by Rosecrans Avenue, east City limits, Alondra Boulevard, Stage Road, and La Mirada Creek.